Progress keeps marching along. All of the windows are in and so are the doors. The installers are measuring for storefront. For now those areas are just filled in with plastic.
Outside of the eelevator lobby they’ve installed Zip R panel on hinges so that can continue to bring supplies into the building. They’ll likely close that in with storefront once the elevator is installed and most of the large items have been brought inside.